House Nearing Completion. (13 Months Of Work)
Officialy started building my friends new home around the first week of April 2006. A 13 months later its still not done but getting much closer. Would have been finshed by now but when weather, money, and time came into the equation it slowed down quite a bit.
Find the beginning here...Click Me!!!
First week of May 2006.

Middle of June 2006. 1st floor completed, floor trusses for 2nd floor all layed and being sheeted.

Late August 2006 about a week after I got back from Taiwan. No pics of the 2nd floor framing, I only helped frame the outer walls before I took off. Started laying the roof trusses the day after I returned. This was taken about 1/2 an hour before a pretty bad storm blew in.

March 2007. Looked like this through the winter. Temporary doors put in. To cold to do anything outside we worked on the inside. The electrical, phone, cable, heating/cooling, and plumbing was all ran. Also insulated the upstairs and part of the downstairs. Drywall on the second floor is almost done. First floor has yet to be started.

And finally Aprill 23rd 2007. All windows were put in this week. There was a problem with the doors and they were taken back. They are now in (no shots with them though.) Looking to finish by the middle of August. Not to bad for a group of us who have built this thing whenever we had free time
In the next couple months the entire outside will be bricked, a 2 story front porch will be built, ground will be sloped and leveled, and the inside will be finished including hard wood floors in all but the bedrooms and bathrooms.
Will post more shots as we begin to finish. Would get some inside shots but its quite a mess at the moment.
Find the beginning here...Click Me!!!
First week of May 2006.

Middle of June 2006. 1st floor completed, floor trusses for 2nd floor all layed and being sheeted.

Late August 2006 about a week after I got back from Taiwan. No pics of the 2nd floor framing, I only helped frame the outer walls before I took off. Started laying the roof trusses the day after I returned. This was taken about 1/2 an hour before a pretty bad storm blew in.

March 2007. Looked like this through the winter. Temporary doors put in. To cold to do anything outside we worked on the inside. The electrical, phone, cable, heating/cooling, and plumbing was all ran. Also insulated the upstairs and part of the downstairs. Drywall on the second floor is almost done. First floor has yet to be started.

And finally Aprill 23rd 2007. All windows were put in this week. There was a problem with the doors and they were taken back. They are now in (no shots with them though.) Looking to finish by the middle of August. Not to bad for a group of us who have built this thing whenever we had free time
In the next couple months the entire outside will be bricked, a 2 story front porch will be built, ground will be sloped and leveled, and the inside will be finished including hard wood floors in all but the bedrooms and bathrooms.
Will post more shots as we begin to finish. Would get some inside shots but its quite a mess at the moment.


Had that house been all brickwork they would have taken a lot longer.